Jerusalem, 26 November, 2026 (TPS-IL) — The Israel Nature and Parks Authority completed the first stage Thursday morning of a special engineering operation at Gador Beach Nature Reserve, near Hadera, involving the controlled demolition of part of the sandstone cliff at Tel Gador.
The operation was designed to eliminate the immediate danger posed by a large rock formation at the top of the cliff that threatened to collapse without warning, potentially endangering beachgoers below.
The work was conducted under close supervision by the Israel Antiquities Authority, in coordination with and with the support of Hadera Municipality.
A new hiking trail will eventually be made accessible along the top of Tel Gador, followed by additional cliff-stabilization work. The parks authority warned that similar dangers exist along much of the coastline between Herzliya and Hadera, urging visitors to stay away from cliff edges and their bases. A recent collapse in Sydney Ali Beach in Herzliya has highlighted the risks.