Jerusalem, 16 November, 2026 (TPS-IL) — An audit of 68 projects worth NIS 377 million ($116 million) found prolonged delays, excessive administrative spending and state-owned companies operating for years without functioning boards, as Israel seeks to revive tourism after the war.
Projects to build promenades, parks and heritage sites intended to attract visitors to Israel routinely take six years or more to complete, while government authorities have failed to properly monitor how the projects are managed, according to a State Comptroller’s report released Monday.
The report by outgoing State Comptroller Matanyahu Englman comes as Israel seeks to revive a tourism industry battered by war. The three companies examined manage public funds for tourism infrastructure projects intended to attract visitors and generate economic activity. Israel’s State Comptroller is an independent oversight authority responsible for auditing government ministries, public bodies and the effectiveness of government policies.
Englman submitted the report to the prime minister and the chairman of the Knesset State Audit Committee in early July, shortly before his term ended. Its publication, required by law within ten weeks, was delayed until the new Knesset was sworn in on Tuesday.
Englman’s audit examined three state-owned companies operating under the Ministry of Tourism. The Government Tourism Company manages tourism infrastructure projects nationwide. The Dead Sea Protection Company is responsible for protecting hotels along the Dead Sea shoreline from flooding, in addition to its tourism-related work. The third company develops tourism sites in Old Acre, a historic walled port city on Israel’s Mediterranean coast and a UNESCO World Heritage site.
Auditors examined 68 projects completed between 2010 and 2025, with a combined estimated value of 377 million shekels. Because neither the ministry nor the companies maintained usable performance data, the Comptroller’s office had to compile its own database.
Projects Took Years to Complete
The findings were stark. Of 49 projects completed by the national company between 2022 and April 2025, between 35% and 49% took six years or longer, while up to 20% took a decade or more. The report found that in 73% of projects with established deadlines, completion took at least twice as long as originally planned. All nine Acre projects examined also exceeded their schedules, by as much as 317%.
The report said the lack of an overall picture “harms the assurance of the principles of efficiency and economy expected in managing public funds and state resources.”
Administrative expenses accounted for between 10.5% and 12.8% of the three companies’ spending in 2025, well above the 4% ceiling set by the Government Companies Authority for comparable state-owned companies.
Governance at two of the companies had largely broken down. Since 2021, the Dead Sea and Acre companies have each operated with just one director, leaving their boards without the minimum number of members required to make legally valid decisions for approximately four and a half years. The report blamed the ministers responsible for failing to appoint additional directors, warning that the lack of functioning boards “harms the proper management of the companies.”
In January, the government approved a merger of the Acre company into the Government Tourism Company and decided to transfer the Dead Sea company’s tourism activities to the national firm as well. Englman criticized the decision-making process, saying it was based on “partial staff work” that considered only potential savings on salaries and suppliers, without examining the companies’ performance or considering alternatives such as hiring private project managers.
Ministry Defends Companies
The companies disputed the Comptroller’s assessment, arguing that many of the delays and financial difficulties resulted from circumstances beyond their control.
The Government Tourism Company said delays “stemmed from circumstances that have no connection to the company,” chiefly local authorities that were slow to secure matching funds or obtain permits.
The Acre company said tourism activity in 2024 and 2025 had fallen to almost zero, sharply reducing its revenue as the war kept foreign visitors away.
The Ministry of Tourism defended the existing model, saying the companies have “professional experience, accumulated expertise and recognized standing.” A shift to private management, it warned, “could lead to the loss of professional knowledge.”
The report also found that a problem identified in a previous audit in 2023 remained unresolved. Agreements with local authorities still contain no penalties for failing to maintain completed tourism sites. Staff at the national company had previously told auditors that “a large majority of the projects do not receive proper maintenance.”
Englman’s seven-year term expired on July 4, though he continued working to finish up certain reports.
The State Comptroller’s post is currently vacant. Michael Rabello, Prime Minister Benjamin Netanyahu’s personal lawyer, was initially confirmed by the Knesset in June. However, the Supreme Court in November ordered the Knesset to hold a new vote after several lawmakes recorded themselves casting ballots on what was supposed to be a secret vote, prompting Rabello withdrew himself from consideration.
Former Supreme Court Justice Yosef Elron, who lost that vote to Rabello, is viewed as a likely successor.